Troy Township Road District Bid Opening – Resurfacing 2026

Location: 25448 Seil Road, Shorewood, IL 60404

Date: Thursday, March 26, 2026

Time: 1:00 p.m.

Meeting Type: Bid Opening

Call to Order

Clerk Larry Ryan called the bid opening to order at 1:00 p.m.

The Pledge of Allegiance was recited.

Attendance

Purpose of Bid Opening

Clerk Ryan stated that the purpose of the bid opening was to open bids for Resurfacing 2026 (milling and resurfacing on County Farm Road and South Rock Run Drive) as advertised for bid in the March 11, 2026, edition of the Joliet Herald News. The bid opening date and time was published in said bid notice as Thursday, March 26, 2026, at 1:00 p.m.

Sealed Bids and Required Documents

Sealed bids will be opened and reviewed for the following:

Bids Received

First Bid – P. T. Ferro Construction Co.

  • Attachment A – Attached
  • Attachment B – Attached
  • IDOT Certificate – Attached
  • Certificate of Insurance (COI) – Attached
  • Proposal on Letterhead – Attached
Schedule of Prices – P. T. Ferro Construction Co.
Item Description Unit Estimated Quantity Unit Price Estimated Total
1. Milling of 1.5 inches Square Yard 12,690 $1.60 $20,304.00
2. Prime Coat Gallon 1,270 $0.01 $12.70
3. Hot-Mix Asphalt (HMA) Surface 2.0 inches Ton 1,425 $78.80 $112,290.00
Bid Total $132,606.70

Second Bid – Austin Tyler Construction, Inc.

  • Attachment A – Attached
  • Attachment B – Attached
  • IDOT Certificate – Attached
  • Certificate of Insurance (COI) – Attached
  • Proposal on Letterhead – Attached
Schedule of Prices – Austin Tyler Construction, Inc.
Item Description Unit Estimated Quantity Unit Price Estimated Total
1. Milling of 1.5 inches Square Yard 13,100 $1.85 $24,235.00
2. Prime Coat Gallon 1,050 $3.00 $3,150.00
3. Hot-Mix Asphalt (HMA) Surface 2.0 inches Ton 1,468 $67.25 $98,723.00
Bid Total $126,108.00

Discussion and Review

Clerk Ryan announced that all bids will be reviewed by Highway Commissioner Ward, who will verify all bids, quantities, and unit prices submitted.

Questions from attendees included the Road District’s estimate at approximately $125,000 and the contract award within a week (pending review). After asking for any other concerns or questions, Ward and Ryan closed the discussion.

Adjournment

Clerk Ryan adjourned the bid opening at 1:07 p.m.

Submission

Respectfully submitted,

Clerk Larry Ryan

Accessibility Disclaimer

This document is designed to meet ADA accessibility standards and provide an inclusive experience for all users. Despite our best efforts, some content may not fully meet every accessibility requirement. If you encounter barriers, need assistance, or require information in an alternative format, please contact us at [email protected].